Great North Road solar farm approved northwest of Newark
Development consent granted for a proposed solar and battery park in Newark and Sherwood, with the Order coming into force in November.
On 27 October 2026, development consent was granted for the Great North Road Solar and Biodiversity Park, northwest of Newark in Newark and Sherwood, Nottinghamshire. Minister Curran made the decision on behalf of the Secretary of State for Energy Security and Net Zero. The applicant, Elements Green Trent Limited, submitted its application on 27 June 2025; it was accepted for examination on 22 July 2025, and the Examining Authority sent its recommendation on 28 July 2026.
The Order authorises a solar photovoltaic generating station, battery energy storage system (BESS), cable connections and associated works. Its National Grid connection would permit the export and import of 800 MW. About 1,025 hectares of the 1,765 hectares within the Order limits would be used for panels and other above-ground works; the remaining area includes below-ground cabling, mitigation and enhancement works. The authorised works also include alteration of the existing Staythorpe substation.
The Order comes into force on 18 November 2026. The decision letter says a judicial-review challenge must be made to the Planning Court within six weeks, starting the day after the Order or decision is published. The decision and examination documents are available on the Planning Inspectorate project page. Consent for a grid-scale project does not by itself change any one household’s bill or tariff.
For local household-scale context, DESNZ’s Regional Renewable Statistics workbook, published on 29 September 2026, records 5,145 solar PV installations and 219.64 MW in Newark and Sherwood at the end of 2025. These are council-wide figures, not a count of homes with panels, and DESNZ says many installations could not yet be assigned to a local authority, so the totals may be revised. PVGIS 5.3 estimates 1,005.0 kWh per kWp a year at the Newark and Sherwood district-centre point; this modelled figure was fetched on 27 October 2026 and is not a prediction for an individual roof.
Browse solar installers in Newark and Sherwood or try the solar payback calculator. For storage and network connections, see our home battery guide and G98 and G99 guide. Read yesterday’s solar installations by council article and today’s PVGIS generation by council article. For the wider project pipeline, see our large solar farms tracker.
Sources
- GOV.UK announcement and Secretary of State decision letter
- Planning Inspectorate project page and Development Consent Order
- DESNZ local-authority statistics and PVGIS 5.3
Source: Great North Road Solar and Biodiversity Park development consent decision announced