Hockerton community agri-solar array gets planning permission
Newark and Sherwood approved Sustainable Hockerton Ltd’s 142-panel scheme beside the village wind turbine, with crops planned between the rows and surplus income intended for local grants.
Newark and Sherwood District Council has granted full planning permission for Sustainable Hockerton Ltd’s community-owned, ground-mounted solar array on land at Kirklington Road, Hockerton, as reported by the Newark Advertiser on 15 November 2026. The council’s application record identifies reference 26/01403/FUL as permitted and records the delegated decision as issued on 2 November 2026.
The council officer’s report describes 142 solar panels on posts in two parallel rows, with clearance for continued agricultural use beneath them. The applicant plans crops such as fruit, vegetables and herbs in the five-metre gap between the tables. Sustainable Hockerton estimates output at about 60 MWh a year. Its planning statement says the power is for the local community; the officer’s report describes it as supplying the existing homes of the Hockerton Housing Project. The scheme replaces an earlier 232-panel application on the same site: the applicant says more efficient panels mean a smaller array can give the same output.
Sustainable Hockerton is a not-for-profit, community-owned cooperative. Its planning statement says its 82 members jointly own Hockerton’s wind turbine and local roof-mounted solar arrays. Project income would cover costs first, with any surplus intended for the community through the group’s grant scheme.
The planning statement names Hockerton Housing Project as scheme manager and says Nottingham Trent University hopes to have two PhD posts linked to the scheme, which were at interview stage when the statement was submitted. Sustainable Hockerton also hopes to work with local oat-drink business DevOATed, which the Newark Advertiser identifies as the project landowner.
A residents’ consultation from November 2024 to February 2025 recorded 19 responses, all from Hockerton residents: 18 supported an array in the village and 16 supported the proposed location. The other one and three respondents respectively wanted more information. This is a snapshot of those who replied, not a village-wide vote.
The officer found the scheme visually acceptable, citing the site’s low position and screening by hedgerows and trees, although it would be visible from the adjacent footpath at close range. Conditions require work to start within three years and follow ecological mitigation in the approved appraisal. If the panels stop operating for 12 continuous months, a decommissioning and removal scheme must be submitted within six months.
Community ownership offers East Midlands households one way to take part in renewable energy alongside home solar. Our planning guide explains when rooftop solar on houses in England is usually permitted development and what limits and exceptions apply; our G98 and G99 guide covers DNO notification for solar and batteries. Find local information on our Newark and Sherwood and Nottinghamshire pages, or browse the solar panel directory.