Guides › Do I need planning permission for solar panels or a heat pump? (England, 2026)

Do I need planning permission for solar panels or a heat pump? (England, 2026)

Last checked: 19 October 2026 12 questions answered

Usually not, if you live in a house in England. Rooftop solar panels, solar panels in the garden, plug-in (balcony) solar, ground source heat pumps and most air source heat pumps are “permitted development” under Part 14 of the General Permitted Development Order, so you do not need to apply for planning permission as long as you stay within its size and location limits. Two recent changes matter: on 29 May 2025 the air source heat pump rules were relaxed (no more 1-metre boundary rule, outdoor units up to 1.5 cubic metres on houses, up to two on detached houses), and on 27 August 2026 the solar rules for houses were rewritten and extended to plug-in solar. Listed buildings and scheduled monuments are excluded, and conservation areas, World Heritage Sites, National Parks and areas of outstanding natural beauty bring extra limits. This page summarises the legislation in plain English; it is not legal advice, so check with your council’s planning team if you are unsure.

Last checked: 19 October 2026. Schemes change, so confirm on GOV.UK before you commit.

Not sure which grant applies to you? Try the 1-minute grant eligibility checker.

Estimate local solar generation and simple payback in the solar payback calculator.

Do I need planning permission for solar panels on my roof?

Usually not for a house in England. Solar PV or solar thermal panels on a house (or a building in its grounds) are permitted development if, on a pitched roof, they stick out no more than 0.2 metres from the roof slope and are no higher than the highest part of the roof (not counting the chimney). On a flat roof the highest part can be no more than 0.6 metres above the highest part of the roof. The house must not be a listed building or on a scheduled monument, and in a conservation area or World Heritage Site the panels cannot go on a wall, balcony or roof enclosure that fronts a road. Panels must be sited, as far as practicable, to minimise their effect on the look of the building and the area, and removed when no longer needed. The Planning Portal advises checking with your council that every limit and condition is met.

Source: GPDO 2015, Schedule 2 Part 14 – renewable energy permitted development (legislation.gov.uk, as amended); The Town and Country Planning (General Permitted Development) (England) (Amendment) Order 2026 (SI 2026/896, in force 27 Aug 2026); Planning Portal – Solar panels: planning permission

What changed for solar panels on 27 August 2026?

SI 2026/896 came into force on 27 August 2026. It splits the solar rules into separate limits for houses and for blocks of flats. For houses it adds limits for panels on walls and on balcony or roof enclosures: no more than 0.2 metres out where the wall or enclosure abuts a road, and no more than 0.4 metres out elsewhere. It brings plug-in solar into the definition of solar PV, so the same permitted development rules apply to it, and it replaces the height rules for solar panels in the garden of a house with a new table. Anything that was permitted development before 27 August 2026 but is not under the new rules can still be carried out until the end of 26 August 2027.

Source: The Town and Country Planning (General Permitted Development) (England) (Amendment) Order 2026 (SI 2026/896, in force 27 Aug 2026); GPDO 2015, Schedule 2 Part 14 – renewable energy permitted development (legislation.gov.uk, as amended)

Is plug-in or balcony solar legal, and do I need permission?

Yes, it is legal. GOV.UK says plug-in solar panels became legal to buy and use across Great Britain from 27 August 2026. The rules cover kits whose microinverter puts out no more than 800W AC, with panels of no more than 2000W DC, a BS 1363 plug going straight into a fixed wall socket, and installation that follows the manufacturer’s instructions. For planning in England, plug-in solar counts as solar PV, so the same wall, balcony, roof and garden limits apply. It is not permitted development if any part goes on a wooden wall, balcony or enclosure or on timber-clad walls, or, in a garden, on a wooden fence, gate or wall. GOV.UK also says to check before you buy whether you need permission from a landlord, building owner or freeholder, planning permission or listed building consent. The government estimates savings of up to £110 a year; your own saving will depend on your home.

Source: GOV.UK news, 26 Aug 2026 – Households can save as plug-in solar panels come to market; Explanatory memorandum to SI 2026/848 – plug-in solar (Plugs and Sockets / ESQCR amendment); The Town and Country Planning (General Permitted Development) (England) (Amendment) Order 2026 (SI 2026/896, in force 27 Aug 2026); GPDO 2015, Schedule 2 Part 14 – renewable energy permitted development (legislation.gov.uk, as amended)

Do I need planning permission for solar panels in my garden?

Usually not, within limits. For a house, ground-mounted (“stand-alone”) solar is permitted development if the panel area is no more than 9 square metres and its height stays within the lowest limit that applies: 1 metre if any part is within 5 metres of the boundary and in front of the main front wall of the house; 2 metres if any part is within 5 metres of the boundary; 2 metres in a conservation area if it is nearer the road than the house; 4 metres otherwise. It cannot be within the grounds of a listed building or on a scheduled monument, and there are extra limits in World Heritage Sites. Before starting, you must ask the council whether it needs to approve the appearance (“prior approval”) if the panels would be in a conservation area and nearer the road than the house, or within 5 metres of the boundary on Article 2(3) land. For blocks of flats, the older rules still apply: one stand-alone array, no more than 4 metres high, at least 5 metres from the boundary, no more than 9 square metres, and no side longer than 3 metres.

Source: GPDO 2015, Schedule 2 Part 14 – renewable energy permitted development (legislation.gov.uk, as amended); The Town and Country Planning (General Permitted Development) (England) (Amendment) Order 2026 (SI 2026/896, in force 27 Aug 2026); GPDO 2015, Schedule 1 Part 1 – Article 2(3) land (legislation.gov.uk)

Do I need planning permission for an air source heat pump?

Usually not. An air source heat pump on a house or block of flats, or in its grounds, is permitted development in England if it complies with the MCS Planning Standards (the MCS 020 a sound calculation) and stays within these limits: only one heat pump on a house that is not detached, or on a block of flats, and up to two on a detached house; an outdoor unit (including any housing) of no more than 1.5 cubic metres on a house or 0.6 cubic metres on a block of flats; not on a pitched roof, and not within 1 metre of the edge of a flat roof; no wind turbine on the same property; not at a listed building or on a scheduled monument. In a conservation area or World Heritage Site it cannot go on a wall or roof that fronts a road, or nearer the road than the house. Elsewhere it cannot go above ground-floor level on a wall that fronts a road. It must not be used only for cooling, must be sited to minimise its effect on the building and the area as far as practicable, and must be removed when no longer needed.

Source: GPDO 2015, Schedule 2 Part 14 – renewable energy permitted development (legislation.gov.uk, as amended); The Town and Country Planning (General Permitted Development) (England) (Amendment) Order 2025 (SI 2025/560), article 5 – air source heat pumps (in force 29 May 2025)

Has the 1-metre rule for heat pumps been scrapped?

Yes. SI 2025/560, in force since 29 May 2025, removed the old requirement that an air source heat pump be at least 1 metre from the property boundary. The same order raised the outdoor unit size limit for houses from 0.6 to 1.5 cubic metres, allowed two heat pumps on a detached house, and allowed heat pumps that cool as well as heat (so air-to-air heat pumps can use the right). The government’s Warm Homes Plan says one installer, Aira, reported the share of customers needing a planning application fell from 30–40% to 5–10% after the change, and that MHCLG and DESNZ will consult in 2026 on further permitted development rights for air source heat pumps. The MCS 020 a sound calculation still applies.

Source: The Town and Country Planning (General Permitted Development) (England) (Amendment) Order 2025 (SI 2025/560), article 5 – air source heat pumps (in force 29 May 2025); GOV.UK – Warm Homes Plan; GPDO 2015, Schedule 2 Part 14 – renewable energy permitted development (legislation.gov.uk, as amended)

What about ground source heat pumps?

Installing a microgeneration ground source heat pump (or a water source heat pump) in the grounds of a house or block of flats is permitted development under Classes C and D of Part 14, which set no extra size or location limits of their own. The general exceptions still apply (see below), and the groundworks for a ground source heat pump at a home currently get 0% VAT.

Source: GPDO 2015, Schedule 2 Part 14 – renewable energy permitted development (legislation.gov.uk, as amended); HMRC – Energy-saving materials and heating equipment (VAT Notice 708/6)

When will I still need to apply for planning permission?

Apply, or at least ask your council first, if your home is a listed building (rooftop and garden solar and air source heat pumps are excluded) or on a scheduled monument; if a front-facing installation is in a conservation area or World Heritage Site; if you are going beyond the size or number limits above; or if a prior approval step applies. That includes solar on a flat roof on Article 2(3) land, and the garden solar cases above. Article 2(3) land means conservation areas, areas of outstanding natural beauty, the Broads, National Parks, World Heritage Sites and some other specified countryside areas. Councils can also remove permitted development rights with an Article 4 direction, or may have removed them in the original planning permission for your home. Listed building consent is a separate permission.

Source: GPDO 2015, Schedule 2 Part 14 – renewable energy permitted development (legislation.gov.uk, as amended); GPDO 2015, Schedule 1 Part 1 – Article 2(3) land (legislation.gov.uk); GOV.UK – Permitted development rights for householders: technical guidance

Can I get paid for the solar electricity I export?

Yes, through the Smart Export Guarantee (SEG), which started on 1 January 2020. Some electricity suppliers (SEG licensees) must offer a tariff to eligible generators, and each supplier sets its own rate and contract length. The rate must always be above zero. Solar PV in Great Britain up to 5MW is eligible. For solar PV up to 50kW you need to show that the installation and the installer are suitably certified, for example with an MCS certificate (Ofgem accepts equivalent schemes accredited to EN 45011 or EN ISO/IEC 17065:2012). You also need an export meter that can take half-hourly readings, and an export MPAN, which your SEG licensee can give you. Your SEG supplier does not have to be your electricity supplier, but you can only use one at a time, and you cannot get SEG and Feed-in Tariff export payments for the same electricity. Ofgem advises shopping around.

Source: Ofgem – Smart Export Guarantee (SEG); Ofgem – SEG: Guidance for Generators

Is there VAT on solar panels and heat pumps?

Installing solar panels, air and ground source heat pumps and other listed energy-saving materials in homes is zero-rated (0% VAT) from 1 May 2023 to 31 March 2027. HMRC says it goes back to the reduced rate of 5% from 1 April 2027. Home EV chargers are not on that list (see our VAT guide for EV chargers).

Source: HMRC – Energy-saving materials and heating equipment (VAT Notice 708/6)

Is there a grant, and how do I check an installer?

For heat pumps, the Boiler Upgrade Scheme in England and Wales pays £7,500 towards an air-to-water or ground source heat pump, or £9,000 in an off-gas-grid home replacing oil or LPG (see our full guide). GOV.UK says to get quotes from MCS-certified installers, and the installer applies to Ofgem for you. Air source heat pumps installed under permitted development must also meet the MCS sound calculation, and SEG payments for solar up to 50kW need suitable certification. Our heat pump directory lists firms that say on their own websites that they offer heat pumps; it does not confirm installer certification. To check that a firm is certified, use MCS’s own Find an Installer search. MCS’s certificate queries page explains how to check that a certificate exists for your installation.

Related: East Midlands heat pump directory

Source: GOV.UK – Boiler Upgrade Scheme: how to apply; GOV.UK – Notice of approved BUS grant categories and values (updated 29 Sep 2026); MCS – Find an Installer (MCS’s own search); MCS – MCS certificate queries; Ofgem – SEG: Guidance for Generators

Does this apply in the East Midlands?

Yes. These permitted development rules are in the Town and Country Planning (General Permitted Development) (England) Order 2015, so they apply across England, including Derbyshire, Nottinghamshire, Leicestershire and Staffordshire. If your home is in a conservation area, National Park or area of outstanding natural beauty, check the extra limits above with your local planning authority before you book (the Planning Portal has a tool to find yours). The SEG and plug-in solar rules apply across Great Britain.

Source: GPDO 2015, Schedule 2 Part 14 – renewable energy permitted development (legislation.gov.uk, as amended); GPDO 2015, Schedule 1 Part 1 – Article 2(3) land (legislation.gov.uk); Planning Portal – Solar panels: planning permission; GOV.UK news, 26 Aug 2026 – Households can save as plug-in solar panels come to market; Ofgem – Smart Export Guarantee (SEG)

Next steps in the East Midlands

Heat pump grant: read the Boiler Upgrade Scheme guide (£7,500 for most air-to-water and ground source heat pumps) or try the grant checker. Grants, VAT and the Smart Export Guarantee are summarised on our grants and tariffs page. Our heat pump directory lists firms that say on their own websites that they offer heat pumps; it does not confirm installer certification. To check certification for a heat pump or solar installer, use MCS’s own Find an Installer. Adding an EV charger too? See planning permission for home EV chargers. For DNO notification or approval for solar panels and home batteries, read our G98 and G99 guide. Already have solar? Our guide to adding a home battery covers the checks before you buy. Local pages: Derbyshire, Nottinghamshire, Leicestershire, Staffordshire.

Ready for quotes?

Choose your area and send a free request to up to three local installers.

Get free quotes

Sources used on this page: GPDO 2015, Schedule 2 Part 14 – renewable energy permitted development (legislation.gov.uk, as amended) · The Town and Country Planning (General Permitted Development) (England) (Amendment) Order 2026 (SI 2026/896, in force 27 Aug 2026) · Planning Portal – Solar panels: planning permission · GOV.UK news, 26 Aug 2026 – Households can save as plug-in solar panels come to market · Explanatory memorandum to SI 2026/848 – plug-in solar (Plugs and Sockets / ESQCR amendment) · GPDO 2015, Schedule 1 Part 1 – Article 2(3) land (legislation.gov.uk) · The Town and Country Planning (General Permitted Development) (England) (Amendment) Order 2025 (SI 2025/560), article 5 – air source heat pumps (in force 29 May 2025) · GOV.UK – Warm Homes Plan · HMRC – Energy-saving materials and heating equipment (VAT Notice 708/6) · GOV.UK – Permitted development rights for householders: technical guidance · Ofgem – Smart Export Guarantee (SEG) · Ofgem – SEG: Guidance for Generators · GOV.UK – Boiler Upgrade Scheme: how to apply · GOV.UK – Notice of approved BUS grant categories and values (updated 29 Sep 2026) · MCS – Find an Installer (MCS’s own search) · MCS – MCS certificate queries