Guides › Home EV charger DNO notification: National Grid (2026)

EV charger DNO notification: do you need to tell National Grid?

Last checked: 18 November 2026 Last reviewed: 18 November 2026 9 questions answered

Yes. Every time a home EV chargepoint is added to an existing supply, the Distribution Network Operator (DNO) must be told. In most straightforward homes the charger can go in first and the installer notifies the DNO within 28 days ("connect and notify"). If your maximum demand is higher, the supply looks inadequate, or there is a safety concern (for example a looped service), the installer must apply and wait for the DNO before fitting the charger. Across Derbyshire, Nottinghamshire, Leicestershire and most of Staffordshire that DNO is National Grid Electricity Distribution (East Midlands or West Midlands licence areas, formerly Western Power Distribution). G98 and G99 are the engineering rules for generation and export (including vehicle-to-grid); ordinary import-only home chargers use the ENA EV chargepoint and heat pump process instead.

Last checked: 18 November 2026. Schemes change, so confirm on GOV.UK before you commit.

Not sure which grant applies to you? Try the 1-minute grant eligibility checker.

Where is the DNO notification form for a home EV charger?

Your installer usually completes and submits the form. As the property owner, make sure the DNO is notified: ask the installer to confirm when the notification or application has been lodged, and keep a copy.

If National Grid Electricity Distribution (NGED) is your DNO, including in the East Midlands licence area and most of Staffordshire, its online form lets you apply to connect a new EV charge point or notify NGED about an existing installation. NGED says it takes around 15 minutes to complete.

Prefer a download? NGED’s official application form is a Word document (.docx), not a PDF. You can return the completed form by email to [email protected] or by post to National Grid Electricity Distribution, Records Team, Lostwithiel Road, Bodmin, PL31 1DE; include any supporting documents requested on the form.

Once it receives the application, NGED says it will reply within 10 working days with next steps; see its Domestic EV page. ENA Connect Direct is the new single online form for installers, not a homeowner account. ENA’s information page explains the route and links to the installer platform.

Sources: GOV.UK – How to register energy devices in homes or small businesses; National Grid Electricity Distribution – Domestic EV; National Grid Electricity Distribution – EV charge point online form; National Grid Electricity Distribution – Single electric vehicle charge point and heat pump application form (Word document); Energy Networks Association – ENA Connect Direct for installers; ENA Connect Direct – Installer platform

Which DNO notification route applies to my home EV charger?

Your installer either fits the charger and notifies the DNO within 28 days or applies first and waits, depending on demand, supply and safety.

The two routes for adding a home EV charger to an existing supply.
RouteWhen it applies and what happensSource
Connect and notifyIf assessed maximum demand is 60A or less per phase, the supply is known to be adequate and there are no safety concerns, the installer may fit the charger and notify the DNO within 28 days.ENA EV and heat pump process
Apply before fittingThe installer applies first if demand exceeds known supply capacity, is above 60A for a typical home, a fuse or cut-out is unsafe or unknown, the supply is looped or unmetered, or an upgrade is needed. For residential demand from 60A to 100A inclusive, ENA says to apply first and aims to confirm within 10 working days.ENA connection FAQs

Compare home, public standard and rapid charging, or a mix, in the EV charging cost calculator.

Is there a PDF of the DNO notification form for a home EV charger?

For NGED homes, the official downloadable <a href="https://connections.nationalgrid.co.uk/downloads/97109/single-electric-vehicle-charge-point-and-heat-pump-installation-application-form-8-.docx">form is a Word document (.docx), not a PDF</a>. NGED also has an <a href="https://connections.nationalgrid.co.uk/lct-ev-charge-point-application">online form</a> to apply for a new charge point or notify an existing installation; it takes around 15 minutes. Your installer usually completes and submits the form, but as the property owner you must make sure the DNO is notified, so ask for confirmation and keep a copy once it is lodged. ENA Connect Direct is the separate <a href="https://connect-direct.energynetworks.org">online form for installers</a> (see <a href="https://www.energynetworks.org/industry/connecting-to-the-networks/connect-direct">ENA’s information</a>), not a homeowner account.

Source: National Grid Electricity Distribution – Domestic EV; National Grid Electricity Distribution – EV charge point online form; National Grid Electricity Distribution – Single electric vehicle charge point and heat pump application form (Word document); GOV.UK – How to register energy devices in homes or small businesses; Energy Networks Association – ENA Connect Direct for installers; ENA Connect Direct – Installer platform

Do I always have to tell the DNO?

Yes. The Energy Networks Association (ENA) says every installer or customer who installs an EV chargepoint on an existing property must inform the network operator, either by notification after the job or by an application beforehand. GOV.UK also lists EV chargepoints among the energy devices that must be registered with your local DNO so the network can manage extra demand safely.

Source: Energy Networks Association – Frequently asked questions about connecting to the networks; GOV.UK – How to register energy devices in homes or small businesses; Energy Networks Association – Connecting electric vehicles and heat pumps to the networks

Can my installer fit the charger before notifying the DNO?

Yes, if the installer assesses that the property's maximum demand including the new charger is 60A or less per phase, the connection is known to be adequate, and there are no safety concerns; they can install the charger and notify the DNO within 28 days. That is the "connect and notify" route on the ENA process. Your installer submits the ENA EV/HP form (often via ENA Connect Direct) or the DNO's own domestic EV form.

Source: Energy Networks Association – Frequently asked questions about connecting to the networks; Energy Networks Association – Connecting electric vehicles and heat pumps to the networks; GOV.UK – Connecting electric vehicle chargepoints to the electricity network

When must the installer apply before fitting the charger?

Contact the DNO in advance when maximum demand is above the known supply capacity, the new demand is above 60A for a typical residential property, the cut-out or fuse looks unsafe or its rating is unknown, the supply is looped or unmetered, or an upgrade is clearly needed. For residential properties with new maximum demand between 60A and 100A inclusive, ENA says the installer must apply before installation and the network operator aims to confirm within 10 working days. GOV.UK summarises the same split: your installer visits, follows the ENA flowchart, and tells you whether the DNO is involved before or after the install.

Source: Energy Networks Association – Frequently asked questions about connecting to the networks; Energy Networks Association – Connecting electric vehicles and heat pumps to the networks; GOV.UK – Connecting electric vehicle chargepoints to the electricity network; GOV.UK – How to register energy devices in homes or small businesses

Who is the DNO for East Midlands homes?

ENA's operator table lists Distributor ID 11 (East Midlands) and ID 14 (West Midlands) as National Grid Electricity Distribution. That covers the East Midlands licence area (roughly Chesterfield to Milton Keynes and Tamworth to the Lincolnshire coast) and the West Midlands licence area, which includes much of Staffordshire. Use ENA's "Who's my network operator?" tool with your postcode or MPAN if you are unsure. National Grid publishes a domestic EV page to apply for a new chargepoint connection or notify an existing installation (email [email protected]).

Source: Energy Networks Association – Connecting electric vehicles and heat pumps to the networks; National Grid Electricity Distribution – Domestic EV; National Grid Electricity Distribution – Electric vehicle charging point

Do G98 and G99 apply to a standard home EV charger?

No. A standard home EV charger that only draws power uses the ENA EV/HP connect-and-notify or apply-to-connect process; G98 and G99 apply to generation and storage that can export. EREC G98 and G99 are ENA engineering recommendations for connecting generation (and storage that can export) in parallel with the public distribution network. G98 covers fully type-tested micro-generation up to 16A (3.68kW) per phase; larger or non-G98 generation uses G99. Vehicle-to-grid (V2G) bi-directional chargepoints are different: GOV.UK says they must be installed and commissioned in line with G98 or G99 depending on capacity, often alongside the EV/HP form.

Source: Energy Networks Association – Connecting generation to the electricity networks (EREC G98 / G99); GOV.UK – How to register energy devices in homes or small businesses

Whose job is it to notify the DNO?

In practice your installer completes and submits the form. GOV.UK is clear that the energy device owner must make sure the DNO has been notified, and that for "apply to connect" jobs the DNO has authorised the work before installation starts. Ask your installer for confirmation (and keep a copy) once the notification or application is lodged.

Source: GOV.UK – How to register energy devices in homes or small businesses; Energy Networks Association – Frequently asked questions about connecting to the networks

Will the DNO refuse my charger?

No. ENA states that network operators are obliged to facilitate the connection of new loads as part of their licence conditions. They may need to upgrade a fuse, cut-out or local cable first. From 1 April 2023, GOV.UK says demand connection customers such as EV chargepoints are no longer charged for distribution network reinforcement to accommodate the connection; you may still pay for equipment that is solely for your own use. Check the connection offer for the breakdown.

Source: Energy Networks Association – Frequently asked questions about connecting to the networks; GOV.UK – Connecting electric vehicle chargepoints to the electricity network

How does this relate to planning and smart chargers?

DNO notification is separate from planning permission and from the Smart Charge Points Regulations. Planning rules for wall chargers and posts (including the 21 October 2026 permitted development changes) are covered in our planning guide. Chargers sold for home use in Great Britain must meet the smart chargepoint rules. Building Regulations Part P still applies to the electrical work.

Source: GOV.UK – Regulations: electric vehicle smart charge points

Who should handle my EV charger DNO notification?

Your installer should handle the DNO form. Compare OZEV-authorised EV charger firms in Derbyshire, Nottinghamshire, Leicestershire or Staffordshire. Related: planning permission, installation cost, smart charger rules, and our grants guide. Confirm eligibility with the grant checker. If you are adding solar panels or a home battery too, read our G98 and G99 guide for solar and batteries.

Ready for quotes?

Choose your area and send a free request to up to three local installers.

Get free quotes

Sources used on this page: National Grid Electricity Distribution – Domestic EV · National Grid Electricity Distribution – EV charge point online form · National Grid Electricity Distribution – Single electric vehicle charge point and heat pump application form (Word document) · GOV.UK – How to register energy devices in homes or small businesses · Energy Networks Association – ENA Connect Direct for installers · ENA Connect Direct – Installer platform · Energy Networks Association – Frequently asked questions about connecting to the networks · Energy Networks Association – Connecting electric vehicles and heat pumps to the networks · GOV.UK – Connecting electric vehicle chargepoints to the electricity network · National Grid Electricity Distribution – Electric vehicle charging point · Energy Networks Association – Connecting generation to the electricity networks (EREC G98 / G99) · GOV.UK – Regulations: electric vehicle smart charge points

Which other home energy guides may help?

These related guides cover other home energy and installation questions.